Town of Leesburg, Virginia
Home Menu
Service Finder
CLOSE
Home Popular Searches
Chesapeake Bay TMDL
For more information about this project, please visit www.leesburgva.gov/tmdl.
Project Description: The Town is required to implement a Chesapeake Bay TMDL (Total Maximum Daily Load) Action Plan to meet the nitrogen, phosphorus, and sediment reduction requirements put in place by the Department of Conservation and Recreation.
This project included retrofitting the Greenway Farm, Foxridge and Stratford stormwater management ponds to provide additional pollutant removal. These retrofits included adding forebays, constructed wetlands, micro-pools, and/or extended detention facilities to the ponds.
Project Contracts:
- Design Engineer: Wood Environment & Infrastructure Solutions, Inc. (formerly Amec Foster Wheeler Earth & Environmental)
- Construction Contractor: Synchronized Construction Services, Inc.
Project Status: This project was completed in July 2018.