Church Street Sidewalk - Missing Link project information from Fiscal Year 2025 Budget (Project No. 27302)  Church St FY25

Project Start Date: Summer 2028 

Estimated Completion Date: Fall 2030

Project Manager: Karin Franklin 703-771-6674

Project Description: This project provides for the installation of approximately 110 feet of 5-foot-wide sidewalk to complete a missing portion of sidewalk on the west side of Church Street between the Church and Market mixed use development and East Market Street. The project includes a utility pole relocation and installation of a retaining wall with stone facade as well as six streetlights including power supply (two on Church Street along the new sidewalk; one at corner of Church Street and East Market Street and three on East Market Street between King Street and Church Street).

Project Updates: There is no funding for this project until Fiscal Year 2029.