South King Street Bridge over Tuscarora Creek Deck Replacement project information from Fiscal Year 2025 Budget (Project No. 23302)S King St Bridge over Tusc Creek Aerial

Project Start Date: Spring 2027

Estimated Completion Date: Summer 2027

Project Manager: Doug Wagner 703-771-6671

Project Description:  The South King Street Bridge over Tuscarora Creek, located immediately south of the Clubhouse Drive intersection was originally constructed in 1952 and was widened in 1970. A recent inspection and analysis of the bridge revealed that the bridge deck and other minor structural elements of the bridge to be in poor condition. It is  forecast that these deficient bridge elements will require repair and/or replacement within the next five years.

Project Updates:  There is no funding for this project until Fiscal Year 2027.