Excavated Materials Holding and Drying Facility

Share & Bookmark, Press Enter to show all options, press Tab go to next option
Print

Excavated Materials Holding and Drying Facility - Public Works Portion project information from Fiscal Year 2025 Budget (Project No. 23107)

Project Start Date: Summer 2022FY20 Excavated Materials Facility

Estimated Completion Date: Spring 2025

Project Manager: Doug Wagner 703-771-6671

Project Description:  This project includes design and construction of a facility to dry materials collected from the Town's vacuum excavation operations, storm drainage vacuum operations, and street sweeper collected debris. This facility is required to meet Virginia Department of Environmental Quality (DEQ) Municipal Separate Storm Sewer System (MS4) requirements. This project is a joint effort between the Department of Public Works and Capital Projects and the Department of Utilities due to the multiple uses of this new facility. This project page represents the Department of Public Works and Capital Projects' contribution. The Department of Utilities' contribution is found in project number 23501.

Project Updates: As of May 17, 2024 - Conceptual design is complete and final design is underway.