Project No. 25503

Project Start Date: Winter 2023FY20 WPCF Dryer Drum Replace

Estimated Completion Date: Winter 2024

Project Manager: Daniel Reeder 703-737-7100

Project Description: Replacement of a 20 year old dryer drum and its associated handling equipment to ensure continued treatment operations and gain efficiency in the biosolids drying process. Replacement of this equipment will ensure the Town's ongoing compliance with regulatory permitting.

Project Updates: As of June 2024 - The dryer drum has been delivered. Andritz is scheduled to install the dryer drum in the fall 2024.