Project No. 28501

Project Start Date: Spring 2024Hogback Tank

Estimated Completion Date: Fall 2027

Project Manager: Russell Chambers 703-771-2728

Project Description: This project will inspect and recoat the Town's Hogback water storage tank. Pending the outcome of an engineer's evaluation, structural repairs to the interior roof support of the tank may be necessary at this time as well. Hogback tank interior and exterior were last recoated in 2010.

Project Updates: As of June 2024 - Design has been awarded to Kimley Horn. The design documents are expected to be completed for spring 2025 and timing for bidding to be determined.