Project No. 29504

Project Start Date: Summer 2028     

Estimated Completion Date: Winter 2030Gravity Thickener Pic

Project Manager:  Russell Chambers 703-771-2728

Project Description: Replacement of the 20 year old sludge thickener tank mechanism to ensure continued operation of the facilities residuals handling process. This equipment operates in a harsh environment where corrosion and mechanical stress negatively impacts asset life.

 

Project Updates: There is no funding for this project until Fiscal Year 2029.