Town of Leesburg, Virginia
Home Menu
Service Finder
CLOSE
Home Popular Searches
Water Treatment Plant Electrical Upgrades
Project No. 23506
Project Start Date: Summer 2022
Estimated Completion Date: Summer 2026
Project Manager: George Brant 703-771-6743
Project Description: Evaluate and replace an existing main electrical switch gear and motor control centers (MCC) installed in 1980 to improve the power feed to the water treatment plant. Replace ancillary breakers that feed critical plant operation equipment. Upgrade electrical equipment to meet technology demands.
Project Updates: As of June 2024 - Final design is complete and the project and will be bid with an anticipated contract award in October 2024.